(TCO 9)&nbspThe Wiscow Manufacturing Company recorded overhead

(TCO 9) The Wiscow Manufacturing Company recorded overhead costs of $14,182 at an activity level of 4,200 machine hours and $8,748 at 2,300 machine hours. The records also indicated that overhead of $9,730 was incurred at 2,600 machine hours. What is the total estimated cost for 2,600 machine hours using the high-low method to estimate the cost equation? (Points : 4)$9,730 $9,606 $9,106 $8,788 Question 4.4. (TCO 8) Southern Company’s budgeted and actual sales for 2009 were: ProductBudgeted SalesActual SalesX20,000 units at $5.00 per unit17,500 units at $5.30 per unitY35,000 units at $9.00 per unit37,300 units at $8.80 per unit What is the total sales variance for the two products? (Points : 4)$2,210 Favorable $5,990 Favorable $6,990 Favorable $8,200 FavorableQuestion 5.5. (TCO 8) Southern Company manufactures Product X.  The standard cost of one unit of output is $12.00 (four pieces at $3.00 per piece).  During the first quarter, 5,000 units were made, at an actual cost of $10.50 per unit (three pieces were $3.50 per piece).  What is the material price variance? (Points : 4)$7,500 Favorable $10,000 Favorable $7,500 Unfavorable $10,000 Unfavorable(PLEASE DOUBLE CHECK WORK/ANSWER  AND MAKE SURE IT’S 110% CORRECT! FINAL ANSWER CAN ONLY BE SUBMITTED ONCE. THANK YOU!)

You can hire someone to answer this question! Yes, essay96.com has paper writers dedicated to completing research and summaries, critical thinking tasks, essays, coursework, and other homework tasks. It's fast and safe.